Modelling building construction durations in Nigeria
Hassan Ahmadu, Ahmadu Bello University, Nigeria.
There is now widespread acceptance in the research community that time prediction models for construction projects should take time-influencing qualitative and managerial factors into consideration. Consequently, several multivariate models combining project scope with these factors have been developed. However, the literature also points to the limitations of these models: their application is only effective in the regions and countries where they were developed. This study aims to develop a multivariate time prediction model that is suitable for the Nigerian construction industry. A self-administered questionnaire was used to source information on the project scope factors and qualitative and managerial factors that should be considered in the study.
Principal component regression was used for the data analysis and model development, using SPSS 16.0 for windows. Three models were developed; two of them - for the public and private sector - had high R2 values. Through testing and validation they were found to be suitable for predicting construction time. By contrast, the third model, which covered all projects, had a low R2 value and was found to be an unsuitable prediction tool. The models with high R2 values serve as a useful tool to help project managers and contractors predict construction time, thereby facilitating effective planning.
This dissertation won the Merit Award, Masters Dissertation Award, CIOB International Innovation & Research Award, 2014.
The judges said, “A well-written dissertation which is tightly written and nicely argued. It draws from a broad and authoritative literature review to frame the research question in an exemplary way. It has a diligent and statistically-rigorous analysis of quantitative data gleaned from a well-designed questionnaire survey. It is an excellent piece of work and is well deserving of international recognition.”
--CIOB
Featured articles and news
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.